Memorial Drive Road Construction
Repaving of
Memorial Drive from Briar Forest to Gessner begins June 9, 2008.
This project involves milling off the old asphalt surface and
applying new asphalt. No widening of Memorial Drive is planned;
however, a left turn lane will be constructed at Sandalwood Drive to
complete the new landscape island. Approaches onto all side streets
off of Memorial will be part of this project and will include
increasing the turning area to help reduce rutting of the grass.
New guard rails and pavement striping will added at the completion
of the project.
The installation of
a left turn lane on northbound Gessner onto westbound Memorial is
also part of this project. This addition will improve efficiency
for the entire intersection and reduce cycle time for all of the
lanes.
All of this work is
expected to be substantially completed before the start of school at
the end of August 2008.
|